[EventId:202402080840_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 February 2024 08:40
Issued by Australian Energy Market Operator Ltd at 0840 hrs on 8 February 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 February 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0840 hrs on 8 February 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024
Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024
At 1850 hrs 07/02/2024 there was an unplanned outage of the South Pine SVC.
The following constraint set(s) invoked at 1855 hrs 07/02/2024
Q-SP_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202402071720_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 February 2024 17:20
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 7 February 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 February 2024.
Refer to market notice: 114422
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1720 hrs on 7 February 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202402071600_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 07 February 2024 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 7 February 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 February 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1600 hrs on 7 February 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Update - Direction - SA Region - 04/02/2024
Update - Direction - SA Region - 04/02/2024
Refer Market Notice 114245
The AEMO intervention event that commenced from interval ending 1635hrs on 04/02/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
QNI Minor testing (NSW to Qld) 7th February 2024
Refer to market notice 113265
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 750 MW on Wednesday 7th February 2024 from 1400 to 1800hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
[EventId:202402071330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 February 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 7 February 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 February 2024.
Refer to market notice: 114412
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 7 February 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202402070835_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 07 February 2024 08:35
Issued by Australian Energy Market Operator Ltd at 0835 hrs on 7 February 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 February 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0835 hrs on 7 February 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024
Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024
At 2102 hrs 06/02/2024 there was an unplanned outage of the Greenbank 275kV SVC
The following constraint set(s) invoked at 2110 hrs 06/02/2024
Q-GB_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations