113480MARKET INTERVENTION19/01/2024 03:19:31 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 113469

The synchronous generating units currently expected to be synchronised in SA from 0005 hrs 20/01/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1530 hrs 19/01/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
113475RECLASSIFY CONTINGENCY19/01/2024 02:24:46 PM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 19/01/2024 14:24

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 113472

Auto-generated on behalf of Manager NEM Real Time Operations
113474MARKET INTERVENTION19/01/2024 05:54:37 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 16/01/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 16/01/2024

Refer Market Notice 113322

The AEMO Intervention Event and all associated directions are cancelled from 1800 hrs 19/01/2024

Manager NEM Real Time Operations
113473RECLASSIFY CONTINGENCY19/01/2024 01:21:51 PM

Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV

Duration: 19/01/2024 13:21 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
113472RECLASSIFY CONTINGENCY19/01/2024 01:21:50 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 19/01/2024 13:21 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
113469MARKET INTERVENTION19/01/2024 01:13:03 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units currently expected to be synchronised in SA from 0130 hrs 20/01/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
113464NON-CONFORMANCE19/01/2024 07:05:14 AM

NON-CONFORMANCE Region NSW1 Friday, 19 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 19 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MP2
Duration: 19/01/2024 07:00 to 19/01/2024 07:05
Amount: 16 MW
Constraint: NC-N_MP2

Auto-generated on behalf of Manager NEM Real Time Operations
113463RECLASSIFY CONTINGENCY18/01/2024 10:13:35 PM

Cancellation of a Non-Credible Contingency Event: H14 Middle Ridge No. 2 and No. 3 275/110 kV transformers in Qld Region due to Lightning

AEMO ELECTRICITY MARKET NOTICE.


Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following elements is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following elements. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD

Elements: H14 Middle Ridge No. 2 and No. 3 275/110 kV transformers

Cancellation time : 2200 hrs 18/01/2024
Constraint set(s) revoked: Q-MR_TX2_3_N-2

Refer AEMO Electricity Market Notice 113418

Manager NEM Real Time Operations
113461RECLASSIFY CONTINGENCY18/01/2024 08:54:45 PM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 18/01/2024 20:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 113427

Auto-generated on behalf of Manager NEM Real Time Operations