113837RECLASSIFY CONTINGENCY27/01/2024 11:23:05 AM

Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Duration: 27/01/2024 11:23 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
113836RECLASSIFY CONTINGENCY27/01/2024 11:23:05 AM

Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Duration: 27/01/2024 11:23 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
113834RECLASSIFY CONTINGENCY27/01/2024 11:00:48 AM

Reclassification of a Non-Credible Contingency Event: Strathmore ? Clare South No.7208 132 kV line and Strathmore ? Clare South tee King Creek No.7128/1 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Strathmore ? Clare South No.7208 132 kV and Strathmore ? Clare South tee King Creek No.7128/1 132 kV

Duration: 27/01/2024 11:00 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
113833RECLASSIFY CONTINGENCY27/01/2024 10:32:35 AM

Reclassification of a Non-Credible Contingency Event: Strathmore ? Clare South No.7208 132 kV line and Strathmore ? Clare South tee King Creek No.7128/2 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Strathmore ? Clare South No.7208 132 kV and Strathmore ? Clare South tee King Creek No.7128/2 132 kV

Duration: 27/01/2024 10:32 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
113803MARKET INTERVENTION26/01/2024 04:47:43 PM

Update - Direction - SA Region - 24/01/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 24/01/2024

Refer Market Notice 113710

The AEMO intervention event that commenced from interval ending 1635 hrs on 24/01/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
113761RECLASSIFY CONTINGENCY26/01/2024 07:09:50 AM

Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Cancellation time: 26/01/2024 07:09

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 113760

Auto-generated on behalf of Manager NEM Real Time Operations
113760RECLASSIFY CONTINGENCY26/01/2024 06:07:50 AM

Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Duration: 26/01/2024 06:07 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
113757RECLASSIFY CONTINGENCY26/01/2024 04:59:46 AM

Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Cancellation time: 26/01/2024 04:59

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 113755

Auto-generated on behalf of Manager NEM Real Time Operations
113756RECLASSIFY CONTINGENCY26/01/2024 05:03:55 AM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - QLD region.

AEMO ELECTRICITY MARKET NOTICE.

AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 113741 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 0500 hrs 26/01/2024.

Manager NEM Real Time Operations