[EventId:202105291630_review] Prices for interval 29-May-2021 16:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 29 May 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 29-May-2021 16:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202105291625_review] Prices for interval 29-May-2021 16:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1620 hrs on 29 May 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 29-May-2021 16:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202105291620_review] Prices for interval 29-May-2021 16:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1615 hrs on 29 May 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 29-May-2021 16:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202105291615_review] Prices for interval 29-May-2021 16:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1610 hrs on 29 May 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 29-May-2021 16:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202105291610_review] Prices for interval 29-May-2021 16:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1605 hrs on 29 May 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 29-May-2021 16:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202105291605_review] Prices for interval 29-May-2021 16:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 29 May 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 29-May-2021 16:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/05/2021
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 86222 has been updated at 1600 hrs to the following:
From 1730 hrs 29/05/2021 to 1800 hrs 29/05/2021.
The contingency forecast capacity reserve requirement is 1442 MW.
The minimum capacity reserve available is 1397 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the Qld Region on 31/05/2021
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the Qld region for the following period:
From 1800 hrs 31/05/2021 to 1830 hrs 31/05/2021.
The forecast capacity reserve requirement is 683 MW.
The minimum capacity reserve available is 607 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region beginning on 31/05/2021
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the Qld region for the following periods:
1. From 1730 hrs 31/05/2021 to 1800 hrs 31/05/2021.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 695 MW.
2. From 1830 hrs 31/05/2021 to 1900 hrs 31/05/2021.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 719 MW.
Manager NEM Real Time Operations