[EventId:202409121035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 12 September 2024 10:35
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 12 September 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 12 September 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202409111325_review] Prices for interval 11-Sep-2024 13:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1320 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111320_review] Prices for interval 11-Sep-2024 13:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111315_review] Prices for interval 11-Sep-2024 13:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1310 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111310_review] Prices for interval 11-Sep-2024 13:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1305 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111305_review] Prices for interval 11-Sep-2024 13:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111300_review] Prices for interval 11-Sep-2024 13:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Tuesday, 10 September 2024
NON-CONFORMANCE QLD1 Region Tuesday, 10 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/09/2024 03:50 to 10/09/2024 04:10
Amount: 39 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 9 September 2024
NON-CONFORMANCE QLD1 Region Monday, 9 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 09/09/2024 17:25 to 09/09/2024 17:40
Amount: -32 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations