Market Notices

115039RESERVE NOTICE23/02/2024 02:56:02 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1730 hrs to 1830 hrs 29/02/2024.
The forecast capacity reserve requirement is 1256 MW.
The minimum capacity reserve available is 1004 MW.

AEMO Operations
115036MARKET SYSTEMS23/02/2024 02:03:13 PM

CHG0082690 | Production | MSATS NEM Reform Metering Exemptions and B2M r44 Schema Go-Live

Change Number: CHG0082690
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS NEM Reform Metering Exemptions and B2M r44 Schema Go-Live
Change Start Date & Time: 03/03/2024 09:00:00 AEST
Change End Date & Time: 03/03/2024 17:00:00 AEST
Outage Start Date & Time: 03/03/2024 10:00:00 AEST
Outage End Date & Time: 03/03/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
115025RESERVE NOTICE23/02/2024 01:21:26 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115016 has been updated at 1315 hrs to the following:

[1.] From 1730 hrs 23/02/2024 to 1900 hrs 23/02/2024.
The forecast capacity reserve requirement is 1256 MW.
The minimum capacity reserve available is 1097 MW.

Manager NEM Real Time Operations
115018MARKET SYSTEMS23/02/2024 11:42:47 AM

CHG0085747 | Pre-Production | Retail Pre-Production Data refresh (CATS and EMDM)

Change Number: CHG0085747
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Retail Pre-Production Data refresh (CATS and EMDM)
Change Start Date & Time: 04/03/2024 08:00:00 AEST
Change End Date & Time: 08/03/2024 19:00:00 AEST
Outage Start Date & Time: 04/03/2024 08:00:00 AEST
Outage End Date & Time: 08/03/2024 19:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: PPD MSATS unavailble betweeb 4th March until cob 8th March 2024
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
115017GENERAL NOTICE23/02/2024 11:34:33 AM

NEM Local Temperature Alerts for SA from 23 Feb 2024 to 27 Feb 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Adelaide West Terrace (39+ Deg C): 27th Feb
Port Augusta Ap (39+ Deg C): 27th Feb

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
115016RESERVE NOTICE23/02/2024 09:49:28 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1800 hrs 23/02/2024 to 1830 hrs 23/02/2024.
The forecast capacity reserve requirement is 1256 MW.
The minimum capacity reserve available is 1231 MW.


Manager NEM Real Time Operations
115015RESERVE NOTICE23/02/2024 09:50:35 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 23/02/2024 to 1830 hrs 23/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1342 MW.


Manager NEM Real Time Operations
115010RESERVE NOTICE23/02/2024 04:50:28 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115009 is cancelled at 0445 hrs 23/02/2024.

Manager NEM Real Time Operations
115009RESERVE NOTICE23/02/2024 02:23:45 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1630 hrs 23/02/2024 to 1800 hrs 23/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1304 MW.


Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm