Market Notices

118500PRICES UNCHANGED28/09/2024 02:21:34 PM

[EventId:202409281410_confirmed] Prices for interval 28-Sep-2024 14:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1420 hrs on 28 September 2024

PRICES ARE NOW CONFIRMED for trading interval 28-Sep-2024 14:10.

In accordance with Market Notice 118495 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118499PRICES UNCHANGED28/09/2024 02:20:25 PM

[EventId:202409281405_confirmed] Prices for interval 28-Sep-2024 14:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1420 hrs on 28 September 2024

PRICES ARE NOW CONFIRMED for trading interval 28-Sep-2024 14:05.

In accordance with Market Notice 118494 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118497PRICES SUBJECT TO REVIEW28/09/2024 02:15:23 PM

[EventId:202409281420_review] Prices for interval 28-Sep-2024 14:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1415 hrs on 28 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 28-Sep-2024 14:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118496PRICES SUBJECT TO REVIEW28/09/2024 02:10:21 PM

[EventId:202409281415_review] Prices for interval 28-Sep-2024 14:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1410 hrs on 28 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 28-Sep-2024 14:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118495PRICES SUBJECT TO REVIEW28/09/2024 02:05:19 PM

[EventId:202409281410_review] Prices for interval 28-Sep-2024 14:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1405 hrs on 28 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 28-Sep-2024 14:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118494PRICES SUBJECT TO REVIEW28/09/2024 02:00:22 PM

[EventId:202409281405_review] Prices for interval 28-Sep-2024 14:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1400 hrs on 28 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 28-Sep-2024 14:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118492PRICES SUBJECT TO REVIEW28/09/2024 01:55:20 PM

[EventId:202409281400_review] Prices for interval 28-Sep-2024 14:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1355 hrs on 28 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 28-Sep-2024 14:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118491PRICES SUBJECT TO REVIEW28/09/2024 01:50:17 PM

[EventId:202409281355_review] Prices for interval 28-Sep-2024 13:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1350 hrs on 28 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 28-Sep-2024 13:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118489GENERAL NOTICE27/09/2024 09:51:41 PM

Network Augmentation Commissioned - NSW Region - 27/09/2024

AEMO ELECTRICITY MARKET NOTICE

A network augmentation has been commissioned in the NSW region at 2150 hrs 27/09/2024 as follows:

Walla Walla substation has been cut into the existing Wagga - Jinderra (62) 330 kV line to form the following circuits:

Jinderra - Walla Walla 62 330 kV Transmission Line
Walla Walla - Wagga 6Y 330 kV Transmission Line

Manager NEM Real Time Operations
     