118479MARKET INTERVENTION27/09/2024 02:54:03 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118476

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1600 hrs 27/09/2024.

The direction update is issued at 1450 hrs 27/09/2024.

Manager NEM Real Time Operations
     
118477MARKET INTERVENTION27/09/2024 02:29:51 PM

Direction - SA region 27/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 27/09/2024

In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1430 hrs 27/09/2024
Type of resource: generating unit
Required actions: to remain synchronised and follow dispatch targets at 0000 hrs 28/09/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 29/09/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118476MARKET INTERVENTION27/09/2024 02:28:25 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118456

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 29/09/2024.

The direction update is issued at 1430 hrs 27/09/2024.

Manager NEM Real Time Operations
     
118475MINIMUM SYSTEM LOAD27/09/2024 10:55:57 AM

Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 118421.

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1030 hrs to 1430 hrs 28/09/2024.

Minimum regional demand is forecast to be 1420 MW at 1200 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
     
118474RESERVE NOTICE26/09/2024 08:01:21 PM

Cancellation of Actual (LOR1) condition in the NSW region - 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 26/09/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.118473 is cancelled at 2000 hrs 26/09/2024.

Manager NEM Real Time Operations
     
118473RESERVE NOTICE26/09/2024 06:48:28 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118472 has been updated at 1850 hrs to the following:

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 996 MW.

Manager NEM Real Time Operations
     
118472RESERVE NOTICE26/09/2024 06:15:18 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

The actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118471 has been updated at 1815 hrs to the following:

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 726 MW.

Manager NEM Real Time Operations
     
118471RESERVE NOTICE26/09/2024 04:41:23 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1440 MW
The minimum capacity reserve available is 1027 MW

Manager NEM Real Time Operations
     
118457MARKET INTERVENTION26/09/2024 05:00:00 PM

Direction - SA region 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 26/09/2024

Refer to Market Notice 118455


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1700 hrs 26/09/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 0800 hrs 27/09/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1600 hrs 27/09/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     