118016INTER-REGIONAL TRANSFER31/08/2024 04:31:20 PM

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV line - NSW region - 31/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV line - NSW region - 31/08/2024

At 1630 hrs 31/08/2024 there was a short notice outage of Armidale - Sapphire 8E 330 kV line.

The following constraint set(s) invoked at 1630 hrs 31/08/2024
N-ARSR_8E, N-TW_SVC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
117969PRICES SUBJECT TO REVIEW29/08/2024 07:25:16 PM

[EventId:202408291930_review] Prices for interval 29-Aug-2024 19:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1925 hrs on 29 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Aug-2024 19:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117968PRICES SUBJECT TO REVIEW29/08/2024 07:20:24 PM

[EventId:202408291925_review] Prices for interval 29-Aug-2024 19:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1920 hrs on 29 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Aug-2024 19:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117965PRICES SUBJECT TO REVIEW29/08/2024 07:15:24 PM

[EventId:202408291920_review] Prices for interval 29-Aug-2024 19:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1915 hrs on 29 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Aug-2024 19:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117963PRICES SUBJECT TO REVIEW29/08/2024 07:10:24 PM

[EventId:202408291915_review] Prices for interval 29-Aug-2024 19:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1910 hrs on 29 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Aug-2024 19:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117962PRICES SUBJECT TO REVIEW29/08/2024 07:05:11 PM

[EventId:202408291910_review] Prices for interval 29-Aug-2024 19:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1905 hrs on 29 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Aug-2024 19:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117961PRICES SUBJECT TO REVIEW29/08/2024 07:00:22 PM

[EventId:202408291905_review] Prices for interval 29-Aug-2024 19:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 29 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Aug-2024 19:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117953PRICES SUBJECT TO REVIEW29/08/2024 05:20:18 PM

[EventId:202408291725_review] Prices for interval 29-Aug-2024 17:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 29 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Aug-2024 17:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117952PRICES SUBJECT TO REVIEW29/08/2024 05:15:21 PM

[EventId:202408291720_review] Prices for interval 29-Aug-2024 17:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1715 hrs on 29 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Aug-2024 17:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     