Market Notices

117033RESERVE NOTICE17/06/2024 09:51:45 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 18/06/2024 to 2030 hrs 18/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1148 MW.

Manager NEM Real Time Operations
     
117032RESERVE NOTICE17/06/2024 03:28:09 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 21/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 0000 hrs to 0030 hrs 21/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1677 MW.

AEMO Operations
     
117031RESERVE NOTICE17/06/2024 03:29:14 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117025 has been updated at 1400 hrs 17/06/2024 to the following:

1. From 0000 hrs to 0100 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1669 MW.

2. From 0600 hrs to 1000 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1651 MW.

3. From 1600 hrs to 2359 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1641 MW.

AEMO Operations
     
117030RESERVE NOTICE17/06/2024 03:27:16 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117024 has been updated at 1400 hrs 17/06/2024 to the following:

1. From 0600 hrs to 0900 hrs 19/06/2024.
The forecast capacity reserve requirement is 1692 MW.
The minimum capacity reserve available is 1565 MW.

2. From 1600 hrs to 2359 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1556 MW.

AEMO Operations
     
117029MARKET SYSTEMS17/06/2024 01:55:46 PM

CHG0089836 | Completed | Pre-Production | Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.

Change Number: CHG0089836
Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal
Service/Component: Gas Hub

Change Title: Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
117028RESERVE NOTICE18/06/2024 10:02:23 AM

RESERVE NOTICE MT PASA PUBLICATION 18 June 2024

The MTPASA result published on 18 June 2024 identifies no Low Reserve Conditions.

Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any AEMO intervention.

For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy

This notice supersedes Market Notice 116909 published on 11 June 2024.

Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.

For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at https://www.aemo.com.au/Electricity/National

Forecasting
AEMO
     
117027GENERAL NOTICE17/06/2024 10:59:14 AM

QNI Minor testing (Qld to NSW) 17th June 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 114742

There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1300 MW on Monday 17th June 2024 from 1200 to 1800hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
     
117026NON-CONFORMANCE17/06/2024 05:25:12 AM

NON-CONFORMANCE Region QLD1 Monday, 17 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 17 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 17/06/2024 04:30 to 17/06/2024 05:25
Amount: -51 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
117025RESERVE NOTICE16/06/2024 02:44:09 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117019 has been updated at 1400 hrs 16/06/2024 to the following:

[2.] From 1600 hrs 19/06/2024 to 0030 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1535 MW.
.

Manager NEM Real Time Operations
     