116741INTER-REGIONAL TRANSFER22/05/2024 12:42:59 PM

Inter-regional transfer limit variation - Para 275kV 1 and 2 275kV SVCs - SA region - 22/05/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Para 275kV 1 and 2 275kV SVCs - SA region - 22/05/2024

At 1300 hrs 22/05/2024 there was a short notice outage of Para 275kV 1 and 2 275kV SVCs.

The following constraint set(s) invoked at 1300 hrs 22/05/2024
S-X_PA_VC_2

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
116740MARKET SYSTEMS22/05/2024 11:04:22 AM

CHG0089859 | Pre-Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.

Change Number: CHG0089859
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas FRC - CATS
Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Change Start Date & Time: 23/05/2024 09:00:00 AEST
Change End Date & Time: 23/05/2024 18:00:00 AEST
Outage Start Date & Time: 23/05/2024 09:00:00 AEST
Outage End Date & Time: 23/05/2024 17:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: The following impacts are expected during this maintenance:
- All access to the VIC & QLD RETAIL GFRC Pre-Production Systems will be unavailable.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
116739NON-CONFORMANCE21/05/2024 05:01:14 PM

NON-CONFORMANCE Region NSW1 Tuesday, 21 May 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 21 May 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW04
Duration: 21/05/2024 16:30 to 21/05/2024 16:35
Amount: -19 MW
Constraint: NC-N_BW04

Auto-generated on behalf of Manager NEM Real Time Operations
     
116738NON-CONFORMANCE21/05/2024 05:00:17 PM

NON-CONFORMANCE Region NSW1 Tuesday, 21 May 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 21 May 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW04
Duration: 21/05/2024 10:45 to 21/05/2024 10:50
Amount: -22 MW
Constraint: NC-N_BW04

Auto-generated on behalf of Manager NEM Real Time Operations
     
116737RESERVE NOTICE21/05/2024 03:29:47 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116724 is cancelled at 1400 hrs 21/05/2024.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
     
116736RESERVE NOTICE21/05/2024 03:30:30 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 22/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116723 is cancelled at 1400 hrs 21/05/2024.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
     
116735INTER-REGIONAL TRANSFER21/05/2024 08:20:42 AM

Update Inter-Regional Transfer limit variation - Basslink 21/05/2024

AEMO ELECTRICITY MARKET NOTICE

Update Inter-Regional Transfer limit variation - Basslink

Refer AEMO Electricity Market Notice 116734

There was an unplanned outage of the Basslink interconnector at 0235 hrs. The Basslink interconnector has been returned to service.

The following constraint set was revoked at 0810 hrs 21/05/2024

I-BL_ZERO

The constraint set contains the following interconnector on the left hand side.

T-V-MNSP1

Manager NEM Real Time Operations
     
116734INTER-REGIONAL TRANSFER21/05/2024 02:51:33 AM

Inter-Regional Transfer limit variation - Basslink 21/05/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Basslink

There has been an unplanned outage of the Basslink interconnector at 0235 hrs

The following constraint set was invoked at 0240 hrs 21/05/2024

I-BL_ZERO

The constraint set contains the following interconnector on the left hand side.

T-V-MNSP1

Manager NEM Real Time Operations
     
116733RESERVE NOTICE20/05/2024 07:13:45 PM

Cancellation of Actual (LOR1) condition in the NSW region - 20/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 20/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116730 is cancelled at 1910 hrs 20/05/2024.

Manager NEM Real Time Operations
     