[EventId:201605230010_confirmed] Prices for interval 23-May-2016 00:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0007 hrs on 23 May 2016
PRICES ARE NOW CONFIRMED for dispatch interval 23-May-2016 00:10.
In accordance with Market Notice 53459 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:201605230010_review] Prices for interval 23-May-2016 00:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 0005 hrs on 23 May 2016
PRICES ARE SUBJECT TO REVIEW for dispatch interval 23-May-2016 00:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2(b) of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:201605230005_confirmed] Prices for interval 23-May-2016 00:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0002 hrs on 23 May 2016
PRICES ARE NOW CONFIRMED for dispatch interval 23-May-2016 00:05.
In accordance with Market Notice 53457 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:201605230005_review] Prices for interval 23-May-2016 00:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 0000 hrs on 23 May 2016
PRICES ARE SUBJECT TO REVIEW for dispatch interval 23-May-2016 00:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2(b) of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region VIC1 Sunday, 22 May 2016
NON-CONFORMANCE VIC1 Region Sunday, 22 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: YWPS2
Duration: 22/05/2016 08:35 to 22/05/2016 08:40
Amount: 20 MW
Constraint: NC-V_YWPS2
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 21 May 2016
Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 21 May 2016
Refer MN 53451
The Tarong to South Pine (832) 275kV Line has been returned to service.
The following constraint set was revoked at 0655 hrs.
Q-TRSP_832
The constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
Cancellation - Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275 kV Line (Qld) - Voltage Control - Saturday, 21 May 2016
Cancellation - Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275 kV Line (Qld) - Voltage Control - Saturday, 21 May 2016
Refer AEMO Electricity Market Notice 53453
The Greenbank to Middle Ridge (8848) 275 kV Line has been returned to service.
Constraint set Q-MRGB_8848_8849 revoked at 0655 hrs.
The constraint set contains equations with the following interconnectors on the LHS:
NSW-QLD1
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control, 21 May 2016
Correction to invoke time
Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - 21 May 2016
The Greenbank to Middle Ridge (8848) 275kV Line has been de-energised to manage voltages in the Qld region.
The following constraint set was invoked at 0140 hrs until further notice.
Q-MRGB_8848_8849
The constraint set contains equations with the following interconnectors on the LHS.
NSW-QLD1
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control
Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - 21 May 2016
The Greenbank to Middle Ridge (8849) 275kV Line has been de-energised to manage voltages in the Qld region.
The following constraint set was invoked at 0225 hrs until further notice.
Q-MRGB_8848_8849
The constraint set contains equations with the following interconnectors on the LHS.
NSW-QLD1
N-Q-MNSP1
Manager NEM Real Time Operations