Market Notices

116684RESERVE NOTICE18/05/2024 05:33:41 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 20/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116667 has been updated at 1730 hrs 18/05/2024 to the following:

[1.] From 1630 hrs 20/05/2024 to 2030 hrs 20/05/2024.
The forecast capacity reserve requirement is 1220 MW.
The minimum capacity reserve available is 900 MW.

[2.] From 2130 hrs 20/05/2024 to 0000 hrs 21/05/2024.
The forecast capacity reserve requirement is 1175 MW.
The minimum capacity reserve available is 1103 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
116683RESERVE NOTICE18/05/2024 05:20:21 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116677 is cancelled at 1715 hrs 18/05/2024.

Manager NEM Real Time Operations
     
116682RECLASSIFY CONTINGENCY18/05/2024 04:49:50 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 18/05/2024 16:49

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 116676

Auto-generated on behalf of Manager NEM Real Time Operations
     
116681RESERVE NOTICE18/05/2024 02:53:22 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 22/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 0530 hrs 22/05/2024 to 0800 hrs 22/05/2024.
The forecast capacity reserve requirement is 1630 MW.
The minimum capacity reserve available is 1334 MW.

[2.] From 1630 hrs 22/05/2024 to 0100 hrs 23/05/2024.
The forecast capacity reserve requirement is 1610 MW.
The minimum capacity reserve available is 1280 MW.

Manager NEM Real Time Operations
     
116680RESERVE NOTICE18/05/2024 02:52:17 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 21/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 0000 hrs 21/05/2024 to 0030 hrs 21/05/2024.
The forecast capacity reserve requirement is 1473 MW.
The minimum capacity reserve available is 1402 MW.

[2.] From 1630 hrs 21/05/2024 to 0100 hrs 22/05/2024.
The forecast capacity reserve requirement is 1600 MW.
The minimum capacity reserve available is 1026 MW.

Manager NEM Real Time Operations
     
116679RESERVE NOTICE18/05/2024 02:48:15 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116650 has been updated at 1430 hrs 18/05/2024 to the following:

[1.] From 0530 hrs 20/05/2024 to 0600 hrs 20/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1281 MW.

Manager NEM Real Time Operations
     
116678RESERVE NOTICE18/05/2024 02:12:26 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116655 has been updated at 1405 hrs to the following:

[1.] From 1700 hrs 18/05/2024 to 1900 hrs 18/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1188 MW.

Manager NEM Real Time Operations
     
116677RESERVE NOTICE18/05/2024 02:10:28 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1730 hrs 19/05/2024 to 1900 hrs 19/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1331 MW.

Manager NEM Real Time Operations
     
116676RECLASSIFY CONTINGENCY18/05/2024 01:44:56 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 18/05/2024 13:44 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     