128166MARKET INTERVENTION18/07/2025 02:32:45 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 128167


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1430 hrs 18/07/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2300 hrs 18/07/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1430 hrs 19/07/2025.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
128165MARKET INTERVENTION18/07/2025 02:10:33 PM

Update 2 - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update 2 - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 128163

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2300 hrs 18/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1430 hrs 18/07/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
128163MARKET INTERVENTION18/07/2025 12:11:23 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 128154

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 18/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 18/07/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
128154MARKET INTERVENTION17/07/2025 06:42:08 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 18/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
128137RESERVE NOTICE16/07/2025 07:24:19 PM

Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 16/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 128136 is cancelled at 1915 hrs 16/07/2025.

Manager NEM Real Time Operations
     
128136RESERVE NOTICE16/07/2025 06:10:16 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/07/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/07/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1257 MW

Manager NEM Real Time Operations
     
128132RESERVE NOTICE15/07/2025 07:11:28 PM

Cancellation of Actual (LOR1) condition in the NSW region - 15/07/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 15/07/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.128131 is cancelled at 1908 hrs 15/07/2025.

Manager NEM Real Time Operations
     
128131RESERVE NOTICE15/07/2025 05:42:16 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/07/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/07/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1025 MW

Manager NEM Real Time Operations
     
128128GENERAL NOTICE14/07/2025 01:43:14 PM

Network Augmentation Commissioned - NSW Region - 14/07/2025

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 14/07/2025

Commissioned:
Buronga No. 1 330 kV/330 kV phase shifting transformer
Buronga No. 2 330 kV/330 kV phase shifting transformer
Buronga No. 3 330 kV/330 kV phase shifting transformer
Buronga No. 4 330 kV/330 kV phase shifting transformer