[EventId:202507251700_review] Prices for interval 25-Jul-2025 17:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1655 hrs on 25 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jul-2025 17:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507251655_review] Prices for interval 25-Jul-2025 16:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1650 hrs on 25 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jul-2025 16:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507251650_review] Prices for interval 25-Jul-2025 16:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 25 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jul-2025 16:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507251645_review] Prices for interval 25-Jul-2025 16:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1640 hrs on 25 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jul-2025 16:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Initial - CHG0104554 - Production eMDM Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management
Change Title: Production eMDM Maintenance Release
Change Start Date & Time: 03/08/2025 10:00:00
Change End Date & Time: 03/08/2025 14:00:00
Outage Start Date & Time: 03/08/2025 10:00:00
Outage End Date & Time: 03/08/2025 14:00:00
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - SA region.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 128312 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 1330 hrs 25/07/2025
Constraint set(s) revoked: I-VS_250
Manager NEM Real Time Operations
Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - SA region.
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely severe weather in the SA region.
AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.
AEMO has taken the following action(s) to maintain power system security at 0850 hrs 25/07/2025.
Constraint set(s) invoked:
I-VS_250
Duration: 0850 hrs until further notice
Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.
Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Duration: 0115 hrs 25/07/2025 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.
Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: SA
Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines
Duration: 0115 hrs 25/07/2025 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations