Market Notices

128225PRICES SUBJECT TO REVIEW22/07/2025 11:50:17 AM

[EventId:202507221155_review] Prices for interval 22-Jul-2025 11:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1150 hrs on 22 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jul-2025 11:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128224PRICES SUBJECT TO REVIEW22/07/2025 11:45:33 AM

[EventId:202507221150_review] Prices for interval 22-Jul-2025 11:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1145 hrs on 22 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jul-2025 11:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128223PRICES SUBJECT TO REVIEW22/07/2025 11:40:17 AM

[EventId:202507221145_review] Prices for interval 22-Jul-2025 11:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1140 hrs on 22 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jul-2025 11:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128222PRICES SUBJECT TO REVIEW22/07/2025 11:35:17 AM

[EventId:202507221140_review] Prices for interval 22-Jul-2025 11:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1135 hrs on 22 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jul-2025 11:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128215NON-CONFORMANCE21/07/2025 06:45:14 PM

NON-CONFORMANCE Region SA1 Monday, 21 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 21 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BLYTHB1
Duration: 21/07/2025 18:40 to 21/07/2025 18:45
Amount: 11 MW
Constraint: NC-S_BLYTHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128213MARKET SYSTEMS21/07/2025 05:08:02 PM

CHG0104553 - Pre-Prod eMDM Maintenance

Change Number: CHG0104553

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
128211MARKET SYSTEMS21/07/2025 04:32:59 PM

CHG0102957|PROD|Enable TLS 1.3 for Gas B2B Hub and disable TLS version 1.0/1.1



The Gas B2B hub servers will be updated to support TLS (Transport Layer Security) 1.3 version. Also the legacy versions 1.0 and 1.1 will be disabled and not be supported going forward.

Participants are required to use TLS 1.2 as a minimum protocol to communicate with AEMO, failing to do so will impact the connectivity. An outage is not expected but, there may be some minor interruptions during the change period.

Participants are required to make sure the connectivity is intact post change implementation.

In case of any issues noticed, please reach out to AEMO Support Hub.
     
128209NON-CONFORMANCE20/07/2025 03:55:18 PM

NON-CONFORMANCE Region QLD1 Sunday, 20 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 20 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 20/07/2025 15:45 to 20/07/2025 15:55
Amount: -51 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
     
128175POWER SYSTEM EVENTS19/07/2025 01:35:42 PM

Non-credible contingency event - TAS region - 19/07/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 19/07/2025

At 1240 hrs the Liapoota - Wadamana - Palmerston 220 kV line and the Cattle Hill Wind Farm - Wadamana 220 kV line tripped.

AEMO did not instruct load shedding.

AEMO has been advised of a 70 MW load reduction at Nyrstar.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm