Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 13/01/2025
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 13/01/2025
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR2 condition is forecast to exist until 1800 hrs
The capacity reserve required is 714 MW
The minimum reserve available is 560 MW
AEMO is seeking an immediate market response.
An insufficient market response may require AEMO to implement a AEMO intervention event.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1700 hrs
The capacity reserve requirement is 1390 MW
The minimum capacity reserve available is 861 MW