Planned outage of Kiamal SF-Red Cliffs 220kV LINE in the VIC region on 27/06/2025
The Kiamal SF-Red Cliffs 220kV LINE line in the Victorian (VIC) region is planned to be out of service from 0700 hrs on 27/06/2025 to 1630 hrs on 27/06/2025.
A credible contingency event during this planned outage may require:
* Load shedding in the Victorian outer grid; and/ or
* Market intervention, such as the issuing of directions.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
[EventId:202506241515_review] Prices for interval 24-Jun-2025 15:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1510 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241510_review] Prices for interval 24-Jun-2025 15:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241505_review] Prices for interval 24-Jun-2025 15:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241500_review] Prices for interval 24-Jun-2025 15:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1455 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241455_review] Prices for interval 24-Jun-2025 14:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 14:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241450_review] Prices for interval 24-Jun-2025 14:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1445 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 14:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231410_review] Prices for interval 23-Jun-2025 14:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 14:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231405_review] Prices for interval 23-Jun-2025 14:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 14:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.