STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 02/07/2025
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 127847 is cancelled at 1600 hrs on 25/06/2025.
No LOR3 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 02/07/2025
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0630 hrs to 1100 hrs 02/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 108 MW at 0800 hrs.
2. From 1700 hrs 02/07/2025 to 0000 hrs 03/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 153 MW at 1900 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Planned outage of Kiamal SF-Red Cliffs 220kV LINE in the VIC region on 27/06/2025
The Kiamal SF-Red Cliffs 220kV LINE line in the Victorian (VIC) region is planned to be out of service from 0700 hrs on 27/06/2025 to 1630 hrs on 27/06/2025.
A credible contingency event during this planned outage may require:
* Load shedding in the Victorian outer grid; and/ or
* Market intervention, such as the issuing of directions.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 30/06/2025
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 127753 is cancelled at 0900 hrs on 24/06/2025.
No LOR3 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 30/06/2025
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period[s]:
[1.] From 0730 hrs 30/06/2025 to 0930 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 87 MW at 0800 hrs.
[2.] From 1700 hrs 30/06/2025 to 2300 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 112 MW at 1900 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Darlington Point - Wagga No.63 330 kV line - NSW region - 23/06/2025
Inter-regional transfer limit variation - Darlington Point - Wagga No.63 330 kV line - NSW region - 23/06/2025
At 1719 hrs 23/06/2025 there was an unplanned outage of Darlington Point - Wagga No.63 330 kV line. The Darlington Point - Balranald No. X5 220 kV line consequently tripped due to a control scheme for the trip of the above line as per design.
The following constraint set(s) invoked at 1725 hrs 23/06/2025
N-DPWG_63_X5
This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 1 Leg of Directlink .
The following constraint set was invoked at 2020 hrs 20/06/2025
N-MBTE_1
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlink No.3 Cable - NSW region - 20/06/2025
Inter-regional transfer limit variation - Directlink No.3 Cable - NSW region - 20/06/2025
A planned outage of Directlink No.3 Cable in the NSW region was scheduled from 0700 hrs 16/06/2025 to 1700 hrs 27/06/2025.
The outage has been completed and Directlink No.3 Cable returned to service at 1210 hrs 20/06/2025
Constraint set(s) revoked: N-MBTE_1
Manager NEM Real Time Operations
Planned outage of Moorabool - Cressy No 1 500 kV line in the VIC region on 19/06/2025
The Moorabool - Cressy No 1 500 kV line in the Victoria (VIC) region is planned to be out of service from 0600 hrs to 1700 hrs on 19/06/2025.
A credible contingency event during this planned outage could cause synchronous separation of the South Australia (SA) region from the rest of the NEM.
During this planned outage:
* Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
* Post contingent FCAS will be sourced within SA following Separation event.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations