128032RESERVE NOTICE08/07/2025 08:08:16 PM

Cancellation of Actual (LOR1) condition in the NSW region - 08/07/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 08/07/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.128020 is cancelled at 2000 hrs 08/07/2025.

Manager NEM Real Time Operations
     
128029SETTLEMENTS RESIDUE08/07/2025 06:30:16 PM

[EventId:202507081830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 July 2025 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 8 July 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 July 2025.

Refer to market notice: 128028

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 8 July 2025.

This is an AEMO autogenerated Market Notice.
     
128028SETTLEMENTS RESIDUE08/07/2025 05:30:33 PM

[EventId:202507081730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 July 2025 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 8 July 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 July 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 8 July 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
128020RESERVE NOTICE08/07/2025 05:25:02 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/07/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/07/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1720 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 924 MW

Manager NEM Real Time Operations
     
128015MARKET INTERVENTION08/07/2025 05:22:32 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 09/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
128012MARKET INTERVENTION08/07/2025 02:45:49 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 128007

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0730 hrs 09/07/2025.

The direction update is issued at 1445 hrs 08/07/2025.

Manager NEM Real Time Operations
     
128009MARKET INTERVENTION08/07/2025 03:00:31 PM

Cancellation - AEMO Intervention Event - SA region 06/07/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 06/07/2025

Refer to Market Notice 127966

The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 08/07/2025.


Manager NEM Real Time Operations
     
128008MARKET INTERVENTION08/07/2025 02:59:59 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127995

Direction is cancelled from: 1500 hrs 08/07/2025

Manager NEM Real Time Operations
     
128007MARKET INTERVENTION08/07/2025 10:56:52 AM

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 128006


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1055 hrs 08/07/2025
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 2200 hrs 08/07/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1430 hrs 09/07/2025.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.