128165MARKET INTERVENTION18/07/2025 02:10:33 PM

Update 2 - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update 2 - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 128163

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2300 hrs 18/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1430 hrs 18/07/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
128164INTER-REGIONAL TRANSFER18/07/2025 12:18:28 PM

Inter-regional transfer limit variation - S3 Greenbank 275 kV SVC - QLD region - 18/07/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - S3 Greenbank 275 kV SVC - QLD region - 18/07/2025

At 1207 hrs 18/07/2025 there was an unplanned outage of S3 Greenbank 275 kV SVC.

The following constraint set(s) invoked at 1215 hrs 18/07/2025
Q-GB_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
128163MARKET INTERVENTION18/07/2025 12:11:23 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 128154

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 18/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 18/07/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
128154MARKET INTERVENTION17/07/2025 06:42:08 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 18/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
128151INTER-REGIONAL TRANSFER17/07/2025 03:15:24 PM

Inter-regional transfer limit variation - Calvale-Halys 8810 275kV LINE - QLD region - 17/07/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Calvale-Halys 8810 275kV LINE - QLD region - 17/07/2025

A planned outage of Calvale-Halys 8810 275kV LINE in the QLD region was scheduled from 2300 hrs 15/07/2025 to 1600 hrs 18/07/2025.

The outage has been completed and Calvale-Halys 8810 275kV LINE returned to service at 1500 hrs 17/07/2025

Constraint set(s) revoked: Q-HACL

Manager NEM Real Time Operations
     
128134INTER-REGIONAL TRANSFER16/07/2025 01:32:26 PM

Inter-regional transfer limit variation - Heywood M1 Transformer - VIC region - 16/07/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Heywood M1 Transformer- VIC region - 16/07/2025

A planned outage of Heywood M1 Transformer in the VIC region was scheduled from 0700 hrs 16/07/2025 to 1800 hrs 16/07/2025.

The outage has been completed and Heywood M1 Transformer returned to service at 1335 hrs 16/07/2025

Constraint set(s) revoked: V-HYTX_M12

Manager NEM Real Time Operations
     
128121MARKET INTERVENTION13/07/2025 04:02:17 PM

Cancellation - AEMO Intervention Event - SA region 12/07/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 12/07/2025

Refer to Market Notice 128101

The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs on 13/07/2025.


Manager NEM Real Time Operations
     
128120MARKET INTERVENTION13/07/2025 04:02:03 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 128102

Direction is cancelled from: 1600 hrs 13/07/2025

Manager NEM Real Time Operations
     
128105INTER-REGIONAL TRANSFER12/07/2025 10:59:10 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 3 Leg of Directlink .

The following constraint set was invoked at 2255 hrs 12/07/2025

N-X_MBTE_3

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     