Filter by category
Filter by Date
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 1 Leg of Directlink .
The following constraint set was invoked at 2020 hrs 20/06/2025
N-MBTE_1
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlink No.3 Cable - NSW region - 20/06/2025
Inter-regional transfer limit variation - Directlink No.3 Cable - NSW region - 20/06/2025
A planned outage of Directlink No.3 Cable in the NSW region was scheduled from 0700 hrs 16/06/2025 to 1700 hrs 27/06/2025.
The outage has been completed and Directlink No.3 Cable returned to service at 1210 hrs 20/06/2025
Constraint set(s) revoked: N-MBTE_1
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/06/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 127637 is cancelled at 1410 hrs 17/06/2025.
Manager NEM Real Time Operations
[EventId:202506171235_confirmed] Prices for interval 17-Jun-2025 12:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 17 June 2025
PRICES ARE NOW CONFIRMED for trading interval 17-Jun-2025 12:35.
In accordance with Market Notice 127630 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506171255_confirmed] Prices for interval 17-Jun-2025 12:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 17 June 2025
PRICES ARE NOW CONFIRMED for trading interval 17-Jun-2025 12:55.
In accordance with Market Notice 127636 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506171250_confirmed] Prices for interval 17-Jun-2025 12:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 17 June 2025
PRICES ARE NOW CONFIRMED for trading interval 17-Jun-2025 12:50.
In accordance with Market Notice 127634 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506171245_confirmed] Prices for interval 17-Jun-2025 12:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 17 June 2025
PRICES ARE NOW CONFIRMED for trading interval 17-Jun-2025 12:45.
In accordance with Market Notice 127632 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506171240_confirmed] Prices for interval 17-Jun-2025 12:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 17 June 2025
PRICES ARE NOW CONFIRMED for trading interval 17-Jun-2025 12:40.
In accordance with Market Notice 127631 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506171230_confirmed] Prices for interval 17-Jun-2025 12:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 17 June 2025
PRICES ARE NOW CONFIRMED for trading interval 17-Jun-2025 12:30.
In accordance with Market Notice 127629 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.