PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 0800 hrs 10/06/2025 to 0900 hrs 10/06/2025.
The forecast capacity reserve requirement is 1166 MW.
The minimum capacity reserve available is 840 MW.
Manager NEM Real Time Operations
INC0145687 - RESOLVED - Frequency Performance Payments (FPP) System
AEMO ELECTRICITY MARKET NOTICE
SERVICE INTERRUPTION - RESOLVED
The service interruption relating to Frequency Performance Payments (FPP) System has been resolved.
The FPP System started normal operations from 00:25 Hrs AEST on 09/06/2025
Default Contribution Factors (DCFs) will be used for Regulation Frequency Control Ancillary Service (FCAS) recovery for the trading intervals where CFs were not calculated. No FPP amount will be paid or due for those Trading Intervals.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
INC0145687 - ALERT - Frequency Performance Payments (FPP) Syste
AEMO ELECTRICITY MARKET NOTICE
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to Frequency Performance Payments (FPP) System.
The service interruption started from 20:25 hrs AEST on 08/06/2025. The participants will experience a delay in receiving FPP factors.
AEMO is working on resolving the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/06/2025
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 127454 has been updated to the following:
[1.] From 0700 hrs 10/06/2025 to 0930 hrs 10/06/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 885 MW.
[2.] From 1630 hrs 10/06/2025 to 1700 hrs 10/06/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 1105 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/06/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127402 has been updated to the following:
[1.] From 1700 hrs 12/06/2025 to 2100 hrs 12/06/2025.
The forecast capacity reserve requirement is 1691 MW.
The minimum capacity reserve available is 1532 MW.
Manager NEM Real Time Operations
Cancellation of the reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.
Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Cancellation time: 2345 hrs 7/06/2025
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 127419
Manager NEM Real Time Operations
Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning .
Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: SA
Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines
Cancellation time: 2345 hrs 7/06/2025
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 127418
Manager NEM Real Time Operations
Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - SA region.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 127450 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 2345 hrs 7/06/2025
Constraint set(s) revoked:
I-VS_250
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following periods:
From 0730 hrs 10/06/2025 to 0900 hrs 10/06/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 925 MW.
AEMO Operations