127474GENERAL NOTICE08/06/2025 12:12:12 AM

Network Augmentation Commissioned - NSW Region - 07/06/2025

AEMO ELECTRICITY MARKET NOTICE

A network augmentation has been commissioned in the NSW region at 2350 hrs 07/06/2025 as follows:

Culcairn Solar Farm substation has been cut into the existing Walla Walla - Wagga 6Y 330 kV Transmission Line to form the following circuits:

Culcairn - Walla Walla 6Y 330 kV Transmission Line
Walla Walla - Wagga 3G 330 kV Transmission Line

Manager NEM Real Time Operations
     
127464PRICES SUBJECT TO REVIEW07/06/2025 04:25:15 PM

[EventId:202506071630_review] Prices for interval 07-Jun-2025 16:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1625 hrs on 7 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127463PRICES SUBJECT TO REVIEW07/06/2025 04:20:16 PM

[EventId:202506071625_review] Prices for interval 07-Jun-2025 16:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1620 hrs on 7 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127462PRICES SUBJECT TO REVIEW07/06/2025 04:15:17 PM

[EventId:202506071620_review] Prices for interval 07-Jun-2025 16:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 7 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127461PRICES SUBJECT TO REVIEW07/06/2025 04:10:17 PM

[EventId:202506071615_review] Prices for interval 07-Jun-2025 16:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1610 hrs on 7 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127460PRICES SUBJECT TO REVIEW07/06/2025 04:05:19 PM

[EventId:202506071610_review] Prices for interval 07-Jun-2025 16:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 7 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127458PRICES SUBJECT TO REVIEW07/06/2025 04:00:22 PM

[EventId:202506071605_review] Prices for interval 07-Jun-2025 16:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 7 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127447RESERVE NOTICE07/06/2025 11:59:12 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127435 has been updated at 1145hrs to the following:

From 0600 hrs 10/06/2025 to 0730 hrs 10/06/2025.
The forecast capacity reserve requirement is 832 MW.
The minimum capacity reserve available is 585 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127435RESERVE NOTICE07/06/2025 07:29:49 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 0630 hrs to 0700 hrs 10/06/2025:
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 585 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm