Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 128007
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0730 hrs 09/07/2025.
The direction update is issued at 1445 hrs 08/07/2025.
Manager NEM Real Time Operations
Electricity Market Management System_PreProd
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Electricity Market Management System_PreProd
Change Title: Update Shareplex NuTCracker resource allocation
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 09/10/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 128005 is cancelled at 1000hrs 08/07/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
Cancellation - AEMO Intervention Event - SA region 06/07/2025
Cancellation - AEMO Intervention Event - SA region 06/07/2025
Refer to Market Notice 127966
The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 08/07/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127995
Direction is cancelled from: 1500 hrs 08/07/2025
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 128006
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1055 hrs 08/07/2025
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 2200 hrs 08/07/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1430 hrs 09/07/2025.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 08/07/2025
Direction - SA region 08/07/2025
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1100 hrs on 08/07/2025.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 09/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 128001 has been updated at 0900 hrs 08/07/2025 to the following:
From 2230 hrs to 2330 hrs 09/07/2025.
The forecast capacity reserve requirement is 566 MW.
The minimum capacity reserve available is 573 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 128002 is cancelled at 0900 hrs 08/07/2025.