Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 22/06/2025 03:04 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 22/06/2025 03:04 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Kamerunga - Barron Gorge 7184 132kV line and Kamerunga - Barron Gorge 7143 132kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Kamerunga - Barron Gorge 7184 132kV and Kamerunga - Barron Gorge 7143 132kV
Duration: 22/06/2025 02:45 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Kamerunga - Barron Gorge 7184 132kV line and Kamerunga - Barron Gorge 7143 132kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Kamerunga - Barron Gorge 7184 132kV and Kamerunga - Barron Gorge 7143 132kV
Cancellation time: 22/06/2025 02:39
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 127684
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Kamerunga - Barron Gorge 7184 132kV line and Kamerunga - Barron Gorge 7143 132kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Kamerunga - Barron Gorge 7184 132kV and Kamerunga - Barron Gorge 7143 132kV
Duration: 22/06/2025 01:38 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 21 June 2025
NON-CONFORMANCE QLD1 Region Saturday, 21 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 21/06/2025 09:10 to 21/06/2025 09:50
Amount: 27 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 20 June 2025
NON-CONFORMANCE VIC1 Region Friday, 20 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS4
Duration: 20/06/2025 01:50 to 20/06/2025 02:10
Amount: -37 MW
Constraint: NC-V_YWPS4
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127651 is cancelled at 1400 hrs 18/06/2025.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
NON-CONFORMANCE Region QLD1 Wednesday, 18 June 2025
NON-CONFORMANCE QLD1 Region Wednesday, 18 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 18/06/2025 14:25 to 18/06/2025 14:40
Amount: -55 MW
Constraint: NC-Q_MPP_1