Non-credible contingency event - QLD region - 18/07/2025
Non-credible contingency event - QLD region - 18/07/2025
At 0825 hrs the H11_Nebo 275/132 kV No.1 Transformer was switched out on a planned outage and the H11_Nebo 275 kV SVC tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 18 July 2025
NON-CONFORMANCE QLD1 Region Friday, 18 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: DDPS1
Duration: 18/07/2025 06:25 to 18/07/2025 06:30
Amount: -14 MW
Constraint: NC-Q_DDPS1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202507162215_confirmed] Prices for interval 16-Jul-2025 22:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025
PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:15.
In accordance with Market Notice 128139 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202507162235_confirmed] Prices for interval 16-Jul-2025 22:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025
PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:35.
In accordance with Market Notice 128143 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202507162230_confirmed] Prices for interval 16-Jul-2025 22:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025
PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:30.
In accordance with Market Notice 128142 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202507162225_confirmed] Prices for interval 16-Jul-2025 22:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025
PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:25.
In accordance with Market Notice 128141 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202507162220_confirmed] Prices for interval 16-Jul-2025 22:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025
PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:20.
In accordance with Market Notice 128140 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202507162210_confirmed] Prices for interval 16-Jul-2025 22:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025
PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:10.
In accordance with Market Notice 128138 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 16/07/2025
The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 128136 is cancelled at 1915 hrs 16/07/2025.
Manager NEM Real Time Operations