Filter by category
Filter by Date
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1700 hrs 14/06/2025 to 1930 hrs 14/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 691 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 17/06/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127536 has been updated at 1012 hrs 14/06/2025 to the following:
[1.] From 0700 hrs 17/06/2025 to 0730 hrs 17/06/2025.
The forecast capacity reserve requirement is 581 MW.
The minimum capacity reserve available is 577 MW.
[2.] From 0800 hrs 17/06/2025 to 0900 hrs 17/06/2025.
The forecast capacity reserve requirement is 562 MW.
The minimum capacity reserve available is 530 MW.
[3.] From 0930 hrs 17/06/2025 to 1000 hrs 17/06/2025.
The forecast capacity reserve requirement is 562 MW.
The minimum capacity reserve available is 559 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 17/06/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 0630 hrs 17/06/2025 to 0800 hrs 17/06/2025.
The forecast capacity reserve requirement is 552 MW.
The minimum capacity reserve available is 514 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127519
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 15/06/2025.
The direction update is issued at 1600 hrs 13/06/2025.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 17/06/2025
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127524 is cancelled at 1400 hrs 13/06/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 16/06/2025
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127532 is cancelled at 1400 hrs 13/06/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 16/06/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 0900 hrs to 1000 hrs 16/06/2025.
The forecast capacity reserve requirement is 845 MW.
The minimum capacity reserve available is 809 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 17/06/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
1. From 1100 hrs to 1130 hrs 17/06/2025.
The forecast capacity reserve requirement is 220 MW.
The minimum capacity reserve available is 178 MW.
2. From 1400 hrs to 1430 hrs 17/06/2025.
The forecast capacity reserve requirement is 270 MW.
The minimum capacity reserve available is 236 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127518.
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1700 hrs 12/06/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0000 hrs 14/06/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 14/06/2025.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations