128355RECLASSIFY CONTINGENCY26/07/2025 05:50:05 AM

Reclassification of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV

Duration: 26/07/2025 05:50 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
128354RECLASSIFY CONTINGENCY26/07/2025 05:31:20 AM

Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA
Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Cancellation time: 0530 hrs 26/07/2025

Constraint set(s) revoked: Nil

Refer AEMO Electricity Market Notice 128303

Manager NEM Real Time Operations
     
128353POWER SYSTEM EVENTS26/07/2025 06:00:15 AM

Non-credible contingency event - NSW region - 26/07/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 26/07/2025

At 0449 hrs the Canberra 132 kV A Bus and the Canberra to Latham A2 132 kV Line tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
128352RECLASSIFY CONTINGENCY26/07/2025 05:16:00 AM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 26/07/2025 05:15 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
128351RECLASSIFY CONTINGENCY26/07/2025 03:09:30 AM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 26/07/2025 03:09

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 128350

Auto-generated on behalf of Manager NEM Real Time Operations
     
128350RECLASSIFY CONTINGENCY26/07/2025 02:07:45 AM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 26/07/2025 02:07 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
128349RECLASSIFY CONTINGENCY26/07/2025 12:39:30 AM

Cancellation of a Non-Credible Contingency Event: Burnie - Port Latta - Smithton 1 110kV line and Burnie - Port Latta - Smithton 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Burnie - Port Latta - Smithton 1 110kV and Burnie - Port Latta - Smithton 2 110kV

Cancellation time: 26/07/2025 00:39

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 128348

Auto-generated on behalf of Manager NEM Real Time Operations
     
128348RECLASSIFY CONTINGENCY25/07/2025 11:35:20 PM

Reclassification of a Non-Credible Contingency Event: Burnie - Port Latta - Smithton 1 110kV line and Burnie - Port Latta - Smithton 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Burnie - Port Latta - Smithton 1 110kV and Burnie - Port Latta - Smithton 2 110kV

Duration: 25/07/2025 23:35 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
128345RECLASSIFY CONTINGENCY25/07/2025 06:05:20 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Cancellation time: 1800 hrs 25/07/2025
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 128304

Manager NEM Real Time Operations
     