PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/06/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 127637 is cancelled at 1410 hrs 17/06/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/06/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 18/06/2025 to 1900 hrs 18/06/2025.
The forecast capacity reserve requirement is 938 MW.
The minimum capacity reserve available is 812 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
[EventId:202506171255_review] Prices for interval 17-Jun-2025 12:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1250 hrs on 17 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jun-2025 12:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506171250_review] Prices for interval 17-Jun-2025 12:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1245 hrs on 17 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jun-2025 12:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506171245_review] Prices for interval 17-Jun-2025 12:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1240 hrs on 17 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jun-2025 12:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506171240_review] Prices for interval 17-Jun-2025 12:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1235 hrs on 17 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jun-2025 12:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506171235_review] Prices for interval 17-Jun-2025 12:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 17 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jun-2025 12:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506171230_review] Prices for interval 17-Jun-2025 12:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1225 hrs on 17 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jun-2025 12:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506171225_review] Prices for interval 17-Jun-2025 12:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1220 hrs on 17 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jun-2025 12:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.