Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 127551
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2300 hrs 15/06/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 15/06/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2300 hrs 15/06/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 12/06/2025
Cancellation - AEMO Intervention Event - SA region 12/06/2025
Refer to Market Notice 127518
The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs on 15/06/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127535
Direction is cancelled from: 0400 hrs 15/06/2025
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 14/06/2025
Cancellation of Actual (LOR1) condition in the QLD region - 14/06/2025
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127542 is cancelled at 1808 hrs 14/06/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/06/2025
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/06/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 724 MW
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 14 June 2025
NON-CONFORMANCE QLD1 Region Saturday, 14 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YARANSF1
Duration: 14/06/2025 11:10 to 14/06/2025 12:05
Amount: 67 MW
Constraint: NC-Q_YARANSF1
Auto-generated on behalf of Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127519
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 15/06/2025.
The direction update is issued at 1600 hrs 13/06/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 13 June 2025
NON-CONFORMANCE NSW1 Region Friday, 13 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: CAPBES1
Duration: 13/06/2025 03:35 to 13/06/2025 04:00
Amount: -35 MW
Constraint: NC-N_CAPBES1
Auto-generated on behalf of Manager NEM Real Time Operations