123615POWER SYSTEM EVENTS23/01/2025 03:09:25 AM

Update - Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 23/01/2025

Refer AEMO Electricity Market Notice 123613

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: NSW

Elements: Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines
Duration: 0250 hrs 23/01/2025 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
123613POWER SYSTEM EVENTS23/01/2025 03:02:44 AM

Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 23/01/2025

At 0240 hrs the Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines tripped and auto reclosed.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
123606SETTLEMENTS RESIDUE22/01/2025 10:00:26 PM

[EventId:202501222200_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 January 2025 22:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2200 hrs on 22 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2025.

Refer to market notice: 123585

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2200 hrs on 22 January 2025.

This is an AEMO autogenerated Market Notice.
     
123602RESERVE NOTICE22/01/2025 08:14:17 PM

Cancellation of Actual (LOR1) condition in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 22/01/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.123589 is cancelled at 2015 hrs 22/01/2025.

Manager NEM Real Time Operations
     
123598RESERVE NOTICE22/01/2025 07:44:15 PM

Cancellation of Actual (LOR2) condition in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the QLD region - 22/01/2025

The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No.123594 is cancelled at 1945 hrs 22/01/2025.

Manager NEM Real Time Operations
     
123596SETTLEMENTS RESIDUE22/01/2025 07:30:28 PM

[EventId:202501221930_NRM_NSW1_QLD1_stopped] NEGRES CONSTRAINT NRM_NSW1_QLD1 ceased operating from 22 January 2025 19:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1930 hrs on 22 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to QLD - 22 January 2025.

Refer to market notice: 123591

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to QLD directional interconnector.

The negative residue constraint NRM_NSW1_QLD1 ceased operating at 1930 hrs on 22 January 2025.

This is an AEMO autogenerated Market Notice.
     
123594RESERVE NOTICE22/01/2025 06:43:09 PM

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 22/01/2025

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1830 hrs.

The Actual LOR2 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 515 MW.
The minimum capacity reserve available is 395 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement an AEMO intervention event.

Manager NEM Real Time Operations
     
123591SETTLEMENTS RESIDUE22/01/2025 06:00:29 PM

[EventId:202501221800_NRM_NSW1_QLD1_started] NEGRES CONSTRAINT NRM_NSW1_QLD1 started operating from 22 January 2025 18:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 22 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to QLD - 22 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to QLD directional interconnector.

The negative residue constraint set NRM_NSW1_QLD1 commenced operating from 1800 hrs on 22 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123589RESERVE NOTICE22/01/2025 05:47:39 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 854 MW
The minimum capacity reserve available is 543 MW

Manager NEM Real Time Operations
     