127484MARKET SYSTEMS09/06/2025 01:25:11 AM

INC0145687 - RESOLVED - Frequency Performance Payments (FPP) System

INC0145687 - RESOLVED - Frequency Performance Payments (FPP) System

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - RESOLVED

The service interruption relating to Frequency Performance Payments (FPP) System has been resolved.

The FPP System started normal operations from 00:25 Hrs AEST on 09/06/2025

Default Contribution Factors (DCFs) will be used for Regulation Frequency Control Ancillary Service (FCAS) recovery for the trading intervals where CFs were not calculated. No FPP amount will be paid or due for those Trading Intervals.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au

AEMO IT Duty Manager
     
127483MARKET SYSTEMS09/06/2025 12:02:59 AM

INC0145687 - ALERT - Frequency Performance Payments (FPP) Syste

INC0145687 - ALERT - Frequency Performance Payments (FPP) System

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - ALERT

AEMO is experiencing a service interruption relating to Frequency Performance Payments (FPP) System.

The service interruption started from 20:25 hrs AEST on 08/06/2025. The participants will experience a delay in receiving FPP factors.

AEMO is working on resolving the issue and will provide updates as more information becomes available.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au


































     
127474GENERAL NOTICE08/06/2025 12:12:12 AM

Network Augmentation Commissioned - NSW Region - 07/06/2025

AEMO ELECTRICITY MARKET NOTICE

A network augmentation has been commissioned in the NSW region at 2350 hrs 07/06/2025 as follows:

Culcairn Solar Farm substation has been cut into the existing Walla Walla - Wagga 6Y 330 kV Transmission Line to form the following circuits:

Culcairn - Walla Walla 6Y 330 kV Transmission Line
Walla Walla - Wagga 3G 330 kV Transmission Line

Manager NEM Real Time Operations
     
127433RESERVE NOTICE06/06/2025 07:56:10 PM

Correction - Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025

AEMO ELECTRICITY MARKET NOTICE

Correction - Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025

Correction to Market Notice 127432

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.127421 is cancelled at 1915 hrs 06/06/2025.

Manager NEM Real Time Operations
     
127432RESERVE NOTICE06/06/2025 07:12:56 PM

Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.127421 is cancelled at 1815 hrs 06/06/2025.

Manager NEM Real Time Operations
     
127421RESERVE NOTICE06/06/2025 05:39:13 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1694 MW
The minimum capacity reserve available is 1692 MW

Manager NEM Real Time Operations
     
127415MARKET SYSTEMS06/06/2025 03:57:35 PM

Completed - CHG0103213 - Scheduled maintenance of Marketnet router in Brisbane

Change Number: CHG0103213

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Local Area Network

Change Title: Scheduled maintenance of Marketnet router in Brisbane

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
127414MARKET SYSTEMS06/06/2025 03:55:29 PM

Initial - CHG0103273 - Scheduled Maintenance on Brisbane Datacentre

Change Number: CHG0103273

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Scheduled Maintenance on Brisbane Datacentre
Change Start Date & Time: 14/06/2025 10:00:00
Change End Date & Time: 14/06/2025 16:00:00
Outage Start Date & Time:
Outage End Date & Time:

Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:

IPWAN Participants - A brief interuption of up to 60 seconds while services are failed over from QLD to NSW Datacenter.

Lan-2-Lan VPN Participants (IPSEC) - Up to 4 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10 for Policy Based VPN's or 202.44.76.12 for Route Based VPN) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10 or 202.44.78.12) prior to this scheduled outage. *** Failure to do so will impact connectivity to Marketnet Services ***.

B2B VPN - No impact is expected.

SSL VPN Participants: None expected as DNS entry will be updated to remove QLD IP.

GASHUB: A brief interuption of up to 60 seconds while services are failover from QLD to NSW Datacenter.

Other Impacts will have been communicated in advance.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127405MARKET SYSTEMS06/06/2025 08:35:43 AM

Completed - CHG0103461 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0103461

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Electricity Market Management System_PreProd

Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm