Market Notices

127486RESERVE NOTICE09/06/2025 01:48:41 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127481 is cancelled at 01:15 hrs. 09/06/2025.

Manager NEM Real Time Operations
     
127485RESERVE NOTICE09/06/2025 01:47:20 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127482 is cancelled at 01:15 hrs. 09/06/2025.

Manager NEM Real Time Operations
     
127482RESERVE NOTICE08/06/2025 07:25:26 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1800 hrs 11/06/2025 to 1900 hrs 11/06/2025.
The forecast capacity reserve requirement is 881 MW.
The minimum capacity reserve available is 856 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
127481RESERVE NOTICE08/06/2025 07:24:25 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127480 has been updated to the following:

[1.] From 0630 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 654 MW.
The minimum capacity reserve available is 608 MW.

[2.] From 1830 hrs 10/06/2025 to 1930 hrs 10/06/2025.
The forecast capacity reserve requirement is 905 MW.
The minimum capacity reserve available is 895 MW.

AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
127480RESERVE NOTICE08/06/2025 06:18:03 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127477 has been updated at 1815 hrs to the following:

[1.] From 0630 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 657 MW.
The minimum capacity reserve available is 619 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127477RESERVE NOTICE08/06/2025 02:24:30 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127447 has been updated at 1415 hrs to the following:

[1.] From 0600 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 728 MW.
The minimum capacity reserve available is 612 MW.

[2.] From 1830 hrs 10/06/2025 to 1930 hrs 10/06/2025.
The forecast capacity reserve requirement is 919 MW.
The minimum capacity reserve available is 900 MW.
AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127447RESERVE NOTICE07/06/2025 11:59:12 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127435 has been updated at 1145hrs to the following:

From 0600 hrs 10/06/2025 to 0730 hrs 10/06/2025.
The forecast capacity reserve requirement is 832 MW.
The minimum capacity reserve available is 585 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127435RESERVE NOTICE07/06/2025 07:29:49 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 0630 hrs to 0700 hrs 10/06/2025:
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 585 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127406POWER SYSTEM EVENTS06/06/2025 08:43:55 AM

Non-credible contingency event - VIC region - 06/06/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 06/06/2025

At 0830 hrs the Wodonga No 2 330kV bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     