Market Notices

128030RECLASSIFY CONTINGENCY08/07/2025 06:58:44 PM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - SA region.

AEMO ELECTRICITY MARKET NOTICE.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 127999 is no longer reasonably possible and accordingly its classification has reverted to non-credible.

Cancellation time: 1905 hrs 08/07/2025

Constraint set(s) revoked: I-VS_250



Manager NEM Real Time Operations
     
128021PRICES SUBJECT TO REVIEW08/07/2025 05:25:12 PM

[EventId:202507081730_review] Prices for interval 08-Jul-2025 17:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 8 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Jul-2025 17:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128019PRICES SUBJECT TO REVIEW08/07/2025 05:20:16 PM

[EventId:202507081725_review] Prices for interval 08-Jul-2025 17:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 8 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Jul-2025 17:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128018PRICES SUBJECT TO REVIEW08/07/2025 05:15:15 PM

[EventId:202507081720_review] Prices for interval 08-Jul-2025 17:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1715 hrs on 8 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Jul-2025 17:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128017PRICES SUBJECT TO REVIEW08/07/2025 05:10:22 PM

[EventId:202507081715_review] Prices for interval 08-Jul-2025 17:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1710 hrs on 8 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Jul-2025 17:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128016PRICES SUBJECT TO REVIEW08/07/2025 05:05:19 PM

[EventId:202507081710_review] Prices for interval 08-Jul-2025 17:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 8 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Jul-2025 17:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128014PRICES SUBJECT TO REVIEW08/07/2025 05:00:17 PM

[EventId:202507081705_review] Prices for interval 08-Jul-2025 17:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 8 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Jul-2025 17:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127999RECLASSIFY CONTINGENCY08/07/2025 02:16:58 AM

Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - SA region.

AEMO ELECTRICITY MARKET NOTICE.

AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely severe weather in the SA region.

AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.

AEMO has taken the following action(s) to maintain power system security at 0220 hrs 08/07/2025.

Constraint set(s) invoked:
I-VS_250

Duration: 0220 hrs until further notice

Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).

Manager NEM Real Time Operations
     
127998RECLASSIFY CONTINGENCY08/07/2025 12:25:04 AM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Duration: 0030 hrs 08/07/2025 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     