Network Augmentation Commissioned - NSW Region - 14/07/2025
Network Augmentation Commissioned - NSW Region - 14/07/2025
Commissioned:
Buronga No. 1 330 kV/330 kV phase shifting transformer
Buronga No. 2 330 kV/330 kV phase shifting transformer
Buronga No. 3 330 kV/330 kV phase shifting transformer
Buronga No. 4 330 kV/330 kV phase shifting transformer
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 12/07/2025
Cancellation - AEMO Intervention Event - SA region 12/07/2025
Refer to Market Notice 128101
The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs on 13/07/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128102
Direction is cancelled from: 1600 hrs 13/07/2025
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 128118 is cancelled at 1338 hrs 13/07/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 0800 hrs 14/07/2025 to 0930 hrs 14/07/2025.
The forecast capacity reserve requirement is 436 MW.
The minimum capacity reserve available is 325 MW.
Manager NEM Real Time Operations
[EventId:202507131030_review] Prices for interval 13-Jul-2025 10:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1025 hrs on 13 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Jul-2025 10:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507131025_review] Prices for interval 13-Jul-2025 10:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1020 hrs on 13 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Jul-2025 10:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507131020_review] Prices for interval 13-Jul-2025 10:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1015 hrs on 13 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Jul-2025 10:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507131015_review] Prices for interval 13-Jul-2025 10:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1010 hrs on 13 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Jul-2025 10:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.