Market Notices

127809RECLASSIFY CONTINGENCY24/06/2025 03:19:28 PM

Cancellation of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Cancellation time: 24/06/2025 15:19

Constraint set(s) revoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 127772

Auto-generated on behalf of Manager NEM Real Time Operations
     
127802PRICES SUBJECT TO REVIEW24/06/2025 03:10:17 PM

[EventId:202506241515_review] Prices for interval 24-Jun-2025 15:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1510 hrs on 24 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127801RECLASSIFY CONTINGENCY24/06/2025 03:09:26 PM

Cancellation of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Cancellation time: 24/06/2025 15:09

Constraint set(s) revoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-GH_RC12_250 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 127768

Auto-generated on behalf of Manager NEM Real Time Operations
     
127800RECLASSIFY CONTINGENCY24/06/2025 03:09:25 PM

Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Cancellation time: 24/06/2025 15:09

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 127769

Auto-generated on behalf of Manager NEM Real Time Operations
     
127799PRICES SUBJECT TO REVIEW24/06/2025 03:05:17 PM

[EventId:202506241510_review] Prices for interval 24-Jun-2025 15:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1505 hrs on 24 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127798RECLASSIFY CONTINGENCY24/06/2025 03:04:25 PM

Cancellation of a Non-Credible Contingency Event: Penola West - South East 1 132kV line and Kincraig - Penola West 1 132kV line in SA1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA1

Lines: Penola West - South East 1 132kV and Kincraig - Penola West 1 132kV

Cancellation time: 24/06/2025 15:04

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 127784

Auto-generated on behalf of Manager NEM Real Time Operations
     
127797PRICES SUBJECT TO REVIEW24/06/2025 03:00:24 PM

[EventId:202506241505_review] Prices for interval 24-Jun-2025 15:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 24 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127796PRICES SUBJECT TO REVIEW24/06/2025 02:55:11 PM

[EventId:202506241500_review] Prices for interval 24-Jun-2025 15:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1455 hrs on 24 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127795RECLASSIFY CONTINGENCY24/06/2025 02:54:25 PM

Cancellation of a Non-Credible Contingency Event: Burnie - Port Latta - Smithton 1 110kV line and Burnie - Port Latta - Smithton 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Burnie - Port Latta - Smithton 1 110kV and Burnie - Port Latta - Smithton 2 110kV

Cancellation time: 24/06/2025 14:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 127767

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm