127657MARKET SYSTEMS18/06/2025 10:50:12 AM

Initial - CHG0104258 - Telco Outage Notification - Telstra Perth PSTN Indial (08 9469 95XX-99XX)

Change Number: CHG0104258

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Perth PSTN Indial (08 9469 95XX-99XX)
Change Start Date & Time: 18/06/2025 02:00:00
Change End Date & Time: 18/06/2025 08:00:00
Outage Start Date & Time: 18/06/2025 02:00:00
Outage End Date & Time: 18/06/2025 06:00:00
Environment: Production
Participant Impact and Requirements: Outage Duration:
1 x 10-minutes outage within the outage window

Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Melbourne).

Action Required:
If a call is in progress and subsequently dropped by the outage, the caller will need to initiate the phone call again.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
     
127656MARKET SYSTEMS18/06/2025 10:47:21 AM

Initial - CHG0103463 - EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0103463

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 19/06/2025 08:00:00
Change End Date & Time: 19/06/2025 22:00:00
Outage Start Date & Time: 19/06/2025 18:00:00
Outage End Date & Time: 19/06/2025 19:00:00
Environment: Production
Participant Impact and Requirements: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities. During the window, delivery of FPP calculations through the participant data model may be delayed at various points.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127655RECLASSIFY CONTINGENCY17/06/2025 10:24:10 PM

Cancellation of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Cancellation time: 17/06/2025 22:24

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 127654

Auto-generated on behalf of Manager NEM Real Time Operations
     
127654RECLASSIFY CONTINGENCY17/06/2025 09:20:11 PM

Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Duration: 17/06/2025 21:20 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
127653RECLASSIFY CONTINGENCY17/06/2025 05:54:10 PM

Cancellation of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Cancellation time: 17/06/2025 17:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 127652

Auto-generated on behalf of Manager NEM Real Time Operations
     
127652RECLASSIFY CONTINGENCY17/06/2025 04:52:01 PM

Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Duration: 17/06/2025 16:51 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
127644PRICES UNCHANGED17/06/2025 12:55:23 PM

[EventId:202506171235_confirmed] Prices for interval 17-Jun-2025 12:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1255 hrs on 17 June 2025

PRICES ARE NOW CONFIRMED for trading interval 17-Jun-2025 12:35.

In accordance with Market Notice 127630 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127643PRICES UNCHANGED17/06/2025 12:55:24 PM

[EventId:202506171255_confirmed] Prices for interval 17-Jun-2025 12:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1255 hrs on 17 June 2025

PRICES ARE NOW CONFIRMED for trading interval 17-Jun-2025 12:55.

In accordance with Market Notice 127636 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127642PRICES UNCHANGED17/06/2025 12:55:23 PM

[EventId:202506171250_confirmed] Prices for interval 17-Jun-2025 12:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1255 hrs on 17 June 2025

PRICES ARE NOW CONFIRMED for trading interval 17-Jun-2025 12:50.

In accordance with Market Notice 127634 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.