STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 30/06/2025
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period[s]:
[1.] From 0730 hrs 30/06/2025 to 0930 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 87 MW at 0800 hrs.
[2.] From 1700 hrs 30/06/2025 to 2300 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 112 MW at 1900 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 0230 hrs to 0400 hrs 01/07/2025.
The forecast capacity reserve requirement is 460 MW.
The minimum capacity reserve available is 230 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 30/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0700 hrs to 0730 hrs 30/06/2025.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 350 MW.
2. From 1000 hrs to 1030 hrs 30/06/2025.
The forecast capacity reserve requirement is 406 MW.
The minimum capacity reserve available is 334 MW.
3. From 1630 hrs to 1700 hrs 30/06/2025.
The forecast capacity reserve requirement is 459 MW.
The minimum capacity reserve available is 230 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 0630 hrs to 0800 hrs 26/06/2025.
The forecast capacity reserve requirement is 1859 MW.
The minimum capacity reserve available is 1515 MW.
2. From 1630 hrs to 2230 hrs 26/06/2025.
The forecast capacity reserve requirement is 1859 MW.
The minimum capacity reserve available is 1381 MW.
AEMO Operations
[EventId:202506231410_review] Prices for interval 23-Jun-2025 14:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 14:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231405_review] Prices for interval 23-Jun-2025 14:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 14:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231400_review] Prices for interval 23-Jun-2025 14:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1355 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 14:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231355_review] Prices for interval 23-Jun-2025 13:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1350 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 13:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231350_review] Prices for interval 23-Jun-2025 13:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1345 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 13:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.