Market Notices

127832RECLASSIFY CONTINGENCY24/06/2025 09:59:26 PM

Cancellation of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Cancellation time: 24/06/2025 21:59

Constraint set(s) revoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-GH_RC12_250 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 127826

Auto-generated on behalf of Manager NEM Real Time Operations
     
127831RECLASSIFY CONTINGENCY24/06/2025 09:59:26 PM

Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Cancellation time: 24/06/2025 21:59

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 127825

Auto-generated on behalf of Manager NEM Real Time Operations
     
127830RECLASSIFY CONTINGENCY24/06/2025 09:34:26 PM

Cancellation of a Non-Credible Contingency Event: Tungatinah-Lake Echo-Waddamana 1 110kV line and Tungatinah-Waddamana 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Tungatinah-Lake Echo-Waddamana 1 110kV and Tungatinah-Waddamana 2 110kV

Cancellation time: 24/06/2025 21:34

Constraint set(s) revoked:
T-TUWA12_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 127814

Auto-generated on behalf of Manager NEM Real Time Operations
     
127828RECLASSIFY CONTINGENCY24/06/2025 09:29:26 PM

Cancellation of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Cancellation time: 24/06/2025 21:29

Constraint set(s) revoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 127817

Auto-generated on behalf of Manager NEM Real Time Operations
     
127827RECLASSIFY CONTINGENCY24/06/2025 09:29:25 PM

Cancellation of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV

Cancellation time: 24/06/2025 21:29

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 127816

Auto-generated on behalf of Manager NEM Real Time Operations
     
127826RECLASSIFY CONTINGENCY24/06/2025 08:54:46 PM

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Duration: 24/06/2025 20:54 until further notice

Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-GH_RC12_250 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
127825RECLASSIFY CONTINGENCY24/06/2025 08:54:45 PM

Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Duration: 24/06/2025 20:54 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
127819RESERVE NOTICE24/06/2025 06:42:59 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region beginning on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 0000 hrs 02/07/2025 to 0400 hrs 02/07/2025.
The forecast capacity reserve requirement is 239 MW.
The minimum capacity reserve available is 193 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
127818RESERVE NOTICE24/06/2025 06:42:48 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 01/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127812 has been updated at 1830 hrs 24/06/2025 to the following:

[1.] From 0400 hrs 01/07/2025 to 1000 hrs 01/07/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 123 MW.

2. From 1700 hrs to 2359 hrs 01/07/2025.
The forecast capacity reserve requirement is 234 MW.
The minimum capacity reserve available is 97 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm