Filter by category
Filter by Date
[EventId:202507081830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 July 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 8 July 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 July 2025.
Refer to market notice: 128028
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 8 July 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202507081730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 July 2025 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 8 July 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 July 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 8 July 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Electricity Market Management System_PreProd
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Electricity Market Management System_PreProd
Change Title: Update Shareplex NuTCracker resource allocation
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Pre-Prod eMDM Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Maintenance Release
Change Start Date & Time: 09/07/2025 13:00:00
Change End Date & Time: 09/07/2025 17:00:00
Outage Start Date & Time: 09/07/2025 13:00:00
Outage End Date & Time: 09/07/2025 17:00:00
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
NON-CONFORMANCE Region QLD1 Friday, 4 July 2025
NON-CONFORMANCE QLD1 Region Friday, 4 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TARONG#3
Duration: 04/07/2025 16:40 to 04/07/2025 16:45
Amount: -18 MW
Constraint: NC-Q_TARONG#3
Auto-generated on behalf of Manager NEM Real Time Operations
Initial - CHG0102957 - Roll out of TLS 1.3 support for Gas B2B Hub and disable TLS versions 1.0/1.1
Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub
Change Title: Roll out of TLS 1.3 support for Gas B2B Hub and disable TLS versions 1.0/1.1
Change Start Date & Time: 03/08/2025 10:00:00
Change End Date & Time: 03/08/2025 14:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The Gas B2B hub servers will be updated to support TLS (Transport Layer Security) 1.3 version. Also the legacy versions 1.0 and 1.1 will be disabled and not be supported going forward. Participants are required to use TLS 1.2 as a minimum protocol to communicate with AEMO, failing to do so will impact the connectivity. An outage is not expected but, there may be some minor interruptions during the change period.
Participants are required to make sure the connectivity is intact post change implementation. In case of any issues noticed, please reach out to AEMO Support Hub.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Initial - CHG0104481 - Update Shareplex NuTCracker resource allocation
Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: Update Shareplex NuTCracker resource allocation
Change Start Date & Time: 08/07/2025 10:00:00
Change End Date & Time: 08/07/2025 17:00:00
Outage Start Date & Time: 08/07/2025 10:00:00
Outage End Date & Time: 08/07/2025 12:00:00
Environment: Pre-Production
Participant Impact and Requirements: The Pre-Production Electricity Market Management System(EMMS) ,Frequency Performance Payments (FPP) ,Gas Supply Hub (GSH) will be unavailable during the scheduled outage window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
NON-CONFORMANCE Region NSW1 Thursday, 3 July 2025
NON-CONFORMANCE NSW1 Region Thursday, 3 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 03/07/2025 14:05 to 03/07/2025 14:10
Amount: 13 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 3 July 2025
NON-CONFORMANCE QLD1 Region Thursday, 3 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: ULPBESS1
Duration: 03/07/2025 10:50 to 03/07/2025 11:00
Amount: 7 MW
Constraint: NC-Q_ULPBESS1
Auto-generated on behalf of Manager NEM Real Time Operations