Inter-regional transfer limit variation - Calvale-Halys 8810 275kV LINE - QLD region - 17/07/2025
Inter-regional transfer limit variation - Calvale-Halys 8810 275kV LINE - QLD region - 17/07/2025
A planned outage of Calvale-Halys 8810 275kV LINE in the QLD region was scheduled from 2300 hrs 15/07/2025 to 1600 hrs 18/07/2025.
The outage has been completed and Calvale-Halys 8810 275kV LINE returned to service at 1500 hrs 17/07/2025
Constraint set(s) revoked: Q-HACL
Manager NEM Real Time Operations
[EventId:202507162235_review] Prices for interval 16-Jul-2025 22:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 2230 hrs on 16 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507162230_review] Prices for interval 16-Jul-2025 22:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 2225 hrs on 16 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507162225_review] Prices for interval 16-Jul-2025 22:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 2220 hrs on 16 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507162220_review] Prices for interval 16-Jul-2025 22:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 2215 hrs on 16 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507162215_review] Prices for interval 16-Jul-2025 22:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 2210 hrs on 16 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507162210_review] Prices for interval 16-Jul-2025 22:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 2205 hrs on 16 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 16/07/2025
The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 128136 is cancelled at 1915 hrs 16/07/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/07/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/07/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1257 MW