127596SETTLEMENTS RESIDUE16/06/2025 11:45:29 AM

[EventId:202506161145_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 June 2025 11:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1145 hrs on 16 June 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 June 2025.

Refer to market notice: 127594

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1145 hrs on 16 June 2025.

This is an AEMO autogenerated Market Notice.
     
127594SETTLEMENTS RESIDUE16/06/2025 11:05:23 AM

[EventId:202506161105_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 June 2025 11:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1105 hrs on 16 June 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 June 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1105 hrs on 16 June 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
127581SETTLEMENTS RESIDUE16/06/2025 10:30:20 AM

[EventId:202506161030_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 June 2025 10:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 16 June 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 June 2025.

Refer to market notice: 127578

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1030 hrs on 16 June 2025.

This is an AEMO autogenerated Market Notice.
     
127578SETTLEMENTS RESIDUE16/06/2025 09:35:29 AM

[EventId:202506160935_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 June 2025 09:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0935 hrs on 16 June 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 June 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0935 hrs on 16 June 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
127573RESERVE NOTICE16/06/2025 07:15:27 AM

Cancellation of Actual (LOR1) condition in the QLD region - 16/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 16/06/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127572 is cancelled at 0715 hrs 16/06/2025.

Manager NEM Real Time Operations
     
127572RESERVE NOTICE16/06/2025 06:44:29 AM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 16/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 16/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 0630 hrs.
The Actual LOR1 condition is forecast to exist until 0730 hrs

The capacity reserve requirement is 700 MW
The minimum capacity reserve available is 638 MW

Manager NEM Real Time Operations
     
127543RESERVE NOTICE14/06/2025 06:10:33 PM

Cancellation of Actual (LOR1) condition in the QLD region - 14/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 14/06/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127542 is cancelled at 1808 hrs 14/06/2025.

Manager NEM Real Time Operations
     
127542RESERVE NOTICE14/06/2025 05:41:52 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 724 MW

Manager NEM Real Time Operations
     
127514RESERVE NOTICE12/06/2025 07:26:15 AM

Cancellation of Actual (LOR1) condition in the QLD region - 12/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 12/06/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127513 is cancelled at 0725 hrs 12/06/2025.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm