Cancellation - Direction - NSW region - 23/06/2025
Cancellation - Direction - NSW region - 23/06/2025
Refer to Market Notice 127745.
The requirement for AEMO to issue a direction to maintain the power system in a secure operating state has ended. All associated directions are cancelled from 1907hrs on 23/06/2025.
Manager NEM Real Time Operations
Direction - NSW region 23/06/2025
Direction - NSW region 23/06/2025
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the NSW region.
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided.
A further market notice will be issued when all directions related to this requirement have been cancelled.
For the purposes of the National Electricity Rules this was a clause 4.8.9 instruction under clause 4.8.9(a).
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 127696
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 25/06/2025.
The direction update is issued at 1500 hrs 23/06/2025.
Manager NEM Real Time Operations
[EventId:202506231410_review] Prices for interval 23-Jun-2025 14:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 14:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231405_review] Prices for interval 23-Jun-2025 14:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 14:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231400_review] Prices for interval 23-Jun-2025 14:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1355 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 14:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231355_review] Prices for interval 23-Jun-2025 13:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1350 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 13:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231350_review] Prices for interval 23-Jun-2025 13:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1345 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 13:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231345_review] Prices for interval 23-Jun-2025 13:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 13:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.