Filter by category
Filter by Date
[EventId:202507221905_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 22 July 2025 19:05
Issued by Australian Energy Market Operator Ltd at 1905 hrs on 22 July 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 July 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1905 hrs on 22 July 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 25/07/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0800 hrs to 1000 hrs 25/07/2025.
The forecast capacity reserve requirement is 830 MW.
The minimum capacity reserve available is 790 MW.
2. From 1030 hrs to 1130 hrs 25/07/2025.
The forecast capacity reserve requirement is 846 MW.
The minimum capacity reserve available is 798 MW.
3. From 1300 hrs to 1330 hrs 25/07/2025.
The forecast capacity reserve requirement is 842 MW.
The minimum capacity reserve available is 837 MW.
4. From 1400 hrs to 1530 hrs 25/07/2025.
The forecast capacity reserve requirement is 839 MW.
The minimum capacity reserve available is 804 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202507212000_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 21 July 2025 20:00
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 21 July 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 21 July 2025.
Refer to market notice: 128216
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 2000 hrs on 21 July 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202507211900_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 21 July 2025 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 21 July 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 21 July 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1900 hrs on 21 July 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202507211830_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 21 July 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 21 July 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 July 2025.
Refer to market notice: 128212
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1830 hrs on 21 July 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202507211630_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 21 July 2025 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 21 July 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 July 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1630 hrs on 21 July 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 16/07/2025
The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 128136 is cancelled at 1915 hrs 16/07/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/07/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/07/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1257 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 15/07/2025
Cancellation of Actual (LOR1) condition in the NSW region - 15/07/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.128131 is cancelled at 1908 hrs 15/07/2025.
Manager NEM Real Time Operations