127922RESERVE NOTICE03/07/2025 10:39:49 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 05/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 0900 hrs to 1100 hrs 05/07/2025.
The forecast capacity reserve requirement is 825 MW.
The minimum capacity reserve available is 789 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations

     
127921MARKET SYSTEMS03/07/2025 07:55:53 AM

CHG0103089 - ERI & STPASA Recall Period Production Release

Change Number: CHG0103089

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: EMMS - Dispatch
Change Title: ERI & STPASA Recall Period Production Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
127920MARKET INTERVENTION03/07/2025 06:19:48 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 04/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
127919RESERVE NOTICE03/07/2025 06:19:08 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 05/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127917 is cancelled at 0616 hrs 03/07/2025.

Manager NEM Real Time Operations
     
127918RESERVE NOTICE03/07/2025 06:19:08 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 04/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127916 is cancelled at 0616 hrs 03/07/2025.

Manager NEM Real Time Operations
     
127917RESERVE NOTICE02/07/2025 04:33:03 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 05/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127915 has been updated at 1600 hrs 02/07/2025 to the following:

1. From 0830 hrs to 1130 hrs 05/07/2025.
The forecast capacity reserve requirement is 858 MW.
The minimum capacity reserve available is 793 MW.

2. From 1500 hrs to 1600 hrs 05/07/2025.
The forecast capacity reserve requirement is 863 MW.
The minimum capacity reserve available is 789 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
127916RESERVE NOTICE02/07/2025 04:32:53 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 04/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1730 hrs to 1930 hrs 04/07/2025.
The forecast capacity reserve requirement is 827 MW.
The minimum capacity reserve available is 800 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
127915RESERVE NOTICE02/07/2025 01:52:37 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 05/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127913 has been updated at 1300 hrs 02/07/2025 to the following:

1. From 0700 hrs to 0800 hrs 05/07/2025.
The forecast capacity reserve requirement is 865 MW.
The minimum capacity reserve available is 850 MW.

2. From 0930 hrs to 1000 hrs 05/07/2025.
The forecast capacity reserve requirement is 861 MW.
The minimum capacity reserve available is 849 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
127913RESERVE NOTICE02/07/2025 11:28:48 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 05/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0630 hrs to 0830 hrs 05/07/2025.
The forecast capacity reserve requirement is 866 MW.
The minimum capacity reserve available is 838 MW.

2. From 0900 hrs to 1000 hrs 05/07/2025.
The forecast capacity reserve requirement is 864 MW.
The minimum capacity reserve available is 840 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.



AEMO Operations

     