123621NON-CONFORMANCE23/01/2025 10:25:24 AM

NON-CONFORMANCE Region QLD1 Thursday, 23 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 23 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 23/01/2025 08:40 to 23/01/2025 10:25
Amount: -35 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
123620RESERVE NOTICE23/01/2025 10:40:22 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 123619 is cancelled at 1000 hrs 23/01/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
123619RESERVE NOTICE23/01/2025 10:09:52 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1830 hrs to 1930 hrs 24/01/2025.
The forecast capacity reserve requirement is 863 MW.
The minimum capacity reserve available is 825 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
123618MARKET INTERVENTION23/01/2025 08:46:10 AM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123582

PPCCGT PELICAN POINT at 1000 hrs 23/01/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is expected to stay in place until 1800 hrs 23/01/2025.

The direction update is issued at 0840 hrs 23/01/2025.

Manager NEM Real Time Operations
123617RECLASSIFY CONTINGENCY23/01/2025 07:04:41 AM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 23/01/2025 07:04

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 123614

Auto-generated on behalf of Manager NEM Real Time Operations
123616NON-CONFORMANCE23/01/2025 06:05:16 AM

NON-CONFORMANCE Region QLD1 Thursday, 23 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 23 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 23/01/2025 05:50 to 23/01/2025 06:05
Amount: 38 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
123615POWER SYSTEM EVENTS23/01/2025 03:09:25 AM

Update - Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 23/01/2025

Refer AEMO Electricity Market Notice 123613

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: NSW

Elements: Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines
Duration: 0250 hrs 23/01/2025 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
123614RECLASSIFY CONTINGENCY23/01/2025 03:00:11 AM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 23/01/2025 03:00 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
123613POWER SYSTEM EVENTS23/01/2025 03:02:44 AM

Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 23/01/2025

At 0240 hrs the Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines tripped and auto reclosed.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations