Filter by category
Filter by Date
Network Augmentation Commissioned - NSW Region - 07/06/2025
A network augmentation has been commissioned in the NSW region at 2350 hrs 07/06/2025 as follows:
Culcairn Solar Farm substation has been cut into the existing Walla Walla - Wagga 6Y 330 kV Transmission Line to form the following circuits:
Culcairn - Walla Walla 6Y 330 kV Transmission Line
Walla Walla - Wagga 3G 330 kV Transmission Line
Manager NEM Real Time Operations
[EventId:202506071630_review] Prices for interval 07-Jun-2025 16:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071625_review] Prices for interval 07-Jun-2025 16:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1620 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071620_review] Prices for interval 07-Jun-2025 16:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1615 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071615_review] Prices for interval 07-Jun-2025 16:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1610 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071610_review] Prices for interval 07-Jun-2025 16:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1605 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071605_review] Prices for interval 07-Jun-2025 16:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following periods:
From 0730 hrs 10/06/2025 to 0900 hrs 10/06/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 925 MW.
AEMO Operations
[EventId:202506061800_review] Prices for interval 06-Jun-2025 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 6 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Jun-2025 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.