Market Notices

127610RECLASSIFY CONTINGENCY17/06/2025 06:54:10 AM

Cancellation of a Non-Credible Contingency Event: Kamerunga - Barron Gorge 7184 132kV line and Kamerunga - Barron Gorge 7143 132kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Kamerunga - Barron Gorge 7184 132kV and Kamerunga - Barron Gorge 7143 132kV

Cancellation time: 17/06/2025 06:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 127609

Auto-generated on behalf of Manager NEM Real Time Operations
     
127609RECLASSIFY CONTINGENCY17/06/2025 04:52:05 AM

Reclassification of a Non-Credible Contingency Event: Kamerunga - Barron Gorge 7184 132kV line and Kamerunga - Barron Gorge 7143 132kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Kamerunga - Barron Gorge 7184 132kV and Kamerunga - Barron Gorge 7143 132kV

Duration: 17/06/2025 04:52 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
127608RECLASSIFY CONTINGENCY16/06/2025 10:54:10 PM

Cancellation of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV

Cancellation time: 16/06/2025 22:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 127607

Auto-generated on behalf of Manager NEM Real Time Operations
     
127607RECLASSIFY CONTINGENCY16/06/2025 09:52:30 PM

Reclassification of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV

Duration: 16/06/2025 21:52 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
127601RESERVE NOTICE16/06/2025 02:13:45 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127599 is cancelled at 1410 hrs 16/06/2025.

Manager NEM Real Time Operations
     
127599RESERVE NOTICE16/06/2025 01:28:23 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 1700 hrs 17/06/2025 to 1730 hrs 17/06/2025.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 389 MW.

[2.] From 1800 hrs 17/06/2025 to 2130 hrs 17/06/2025.
The forecast capacity reserve requirement is 633 MW.
The minimum capacity reserve available is 478 MW.

Manager NEM Real Time Operations
     
127593PRICES UNCHANGED16/06/2025 11:00:20 AM

[EventId:202506161040_confirmed] Prices for interval 16-Jun-2025 10:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1100 hrs on 16 June 2025

PRICES ARE NOW CONFIRMED for trading interval 16-Jun-2025 10:40.

In accordance with Market Notice 127582 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127592PRICES UNCHANGED16/06/2025 11:00:20 AM

[EventId:202506161100_confirmed] Prices for interval 16-Jun-2025 11:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1100 hrs on 16 June 2025

PRICES ARE NOW CONFIRMED for trading interval 16-Jun-2025 11:00.

In accordance with Market Notice 127587 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127591PRICES UNCHANGED16/06/2025 11:00:20 AM

[EventId:202506161055_confirmed] Prices for interval 16-Jun-2025 10:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1100 hrs on 16 June 2025

PRICES ARE NOW CONFIRMED for trading interval 16-Jun-2025 10:55.

In accordance with Market Notice 127586 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     