123180RESERVE NOTICE13/01/2025 06:20:05 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025

Refer market notice: 123171

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1365 MW.
The minimum capacity reserve available is 966 MW.

Manager NEM Real Time Operations
123171RESERVE NOTICE13/01/2025 04:58:29 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1700 hrs

The capacity reserve requirement is 1390 MW
The minimum capacity reserve available is 861 MW